Page 29 - NAVAL FORCES 03/2017
P. 29

T echnology Spotlight

        Warner” (SSN 785) provides the best and most   construction span;  and redesigning speci fic
        recent example of getting ships to the fleet ear-  portions of the submarine to reduce acquisi-
        lier.  “’John Warner’ completed its PDWP in   tion cost and/or construction time. DFA began
        just under six months and therefore was just   with the Block III construction contract and the
        eleven months from delivery to its Fleet Read­  end cost of each successive Block III subma-
        iness Training Plan, proving the programme is   rine has been lower than its predecessor. The
        on track to turn ships over to the fleet in less   Block III contract reduced contract   delivery
        than six  years. The  USS ‘Illinois’ (SSN 786)   time from 74 to 66 months, and the Block IV
        PDWP is planned to begin in February and is   boats are doing even better – 62 months for the
          currently scheduled to last six months.”   first three hulls and 60 for the remaining hulls.
          One of the key goals of the VCS has been   The first three of the eight Block III ships (and
        the reduction of total ownership costs, espe-  the first to incorporate DFA changes), USS
        cially Block IV, which has incorporated design   “North Dakota” (SSN 784), “John  Warner,”
        changes to achieve better operational availa-  and “Illinois” (SSN 786), all delivered early to
        bility.  “The programme identified technical   contract, within budget, and with the same or
        barriers and determined the actions required   increased capability.
        to extend the operating cycle from 72 to 96   One of the DFA initiatives included a rede-
        months,” Stevens explained. “Decreasing the   sign of the sonar. “The Large Aperture Bow   Machinist Mate inspects a torpedo silo
        future number of major shipyard availabilities   (LAB) array, utilised on Block III and later   aboard the “Virginia” class fast attack
        from four to three over the service life of the   submarines, uses a water­backed array vice   submarine USS “North Carolina” (SSN-777).
        submarine  results  in  significant  operational   the air­backed spherical sonar array used on   (Photo: US Navy/Mass Communication
        and support [O&S] cost­savings over the life   earlier submarines,” Stevens points out. “The   Specialist 3rd Class Liam Kennedy)
        of a ship. Reduced availabilities allow an in­  shift to the LAB array reduces manufacturing
        crease in the number of deployments from 14   costs associated with the complex machining
        to 15 per ship as the submarines spend less   and ship construction requirements of a spher­  Starting with Block V boats, the submarines
        time in maintenance periods and more time at   ical array and incorporates life­of­ship hydro­  will have an 84ft long VPM inserted into the
        sea”                                phones, further reducing maintenance costs.   submarine in order to add four 87in launch
          One  example offered by Stevens is  the   The LAB array also provides improved passive   tubes. Located inside the pressure hull, the
        change made to the material for the propulsor   sonar capabilities over earlier designs”   tubes will be accessible for the crew to inspect,
        to increase longevity and reduce maintenance   The first ships of the class had 12 single-   maintain or update the weapons.  The  VPM
        requirements. The majority of the remaining   purpose vertical launch system (VLS) missile   programme is making significant progress, in-
        changes were small modifications to pumps,   tubes in the bow section. Current ships have   cluding approval of all key decisions and ship
        valves, coatings, etc. designed to increase the   two  large-diameter Virginia  Payload Tubes   specifications, with a goal of 89 percent of
        periods between maintenance events. The ad-  (VPTs), each capable of launching six TOM-  module design complete at construction start.
        ditional operating capability and O&S savings   AHAWK missiles utilising the same Multiple   The first payload tubes are scheduled to begin
        will be realised as Block IV and later hulls are   All-Up-Round Canisters (MAC) currently   fabrication this year.
        delivered to the fleet and during their service   used  on  the  USN’s  four  guided-missile  sub-  Stevens said that the VPM is a great exam-
        lives. The USN has instituted a three-element   marines. The VPTs are simpler and have fewer   ple of flexible shipbuilding. “To add an 84ft
        effort to reduce costs. The Design for Afforda-  hull openings. The next step in the evolution   module into a 374ft submarine is pretty im­
        bility (DFA) initiative calls for increasing pro-  of the VCS  is the Virginia Payload Module   pressive. It is going to really change the nature
        duction to two ships per year under more eco-  (VPM), which will increase the vertical launch   of that ship and its capacity, firepower and its
        nomical multi-year procurement; reducing the   tubes on each sub from 12 to 40.  overall capability.”  NAFO

































        NAVAL FORCES III/2017                                                                                  27
   24   25   26   27   28   29   30   31   32   33   34